Page 19 - Cover options
P. 19

JSW ENERGY BOLT  |  ISSUE 2

        Auxiliary Power Reduction During Part Load


        Operation Of 300 MW Unit




        How  and Why  was  the  problem                         In CHP, Bunker ventilation system (BVS) is
        identified?                                             crucial in de-dusting activity. As BVS is

                                                                required to be operated along with
        SBU-2 300 MW units are operated at part
                                                                conveyors during coal feeding, at times it
        load due to low schedule. As units
                                                                used to be run continuously without coal
        operating at part load will have impact on
                                                                on  conveyor, which  is  not  required.  This
        cost  of  generation  due  to  high  Auxiliary
                                                                loss was eliminated by fixing an alarm in
        power consumption (APC) and Heat rate.
                                                                PLC to alert operator to stop BVS when
        Since one of the unit being operated at 150
                                                                coal is not fed.
        MW most of the time during a day,
                                                                Operating common CW pump during part
        APC was accounting to 8.25%. Continuous
                                                                load not only resulted in savings on
        monitoring, analysis and brainstorming
                                                                running unit, but at the same time, flow
        sessions helped in identifying potential for
                                                                can be established to reserve shutdown
        energy savings and reduction in APC.
                                                                unit for circulation, thus running of
        Major Contributors for high APC identified
                                                                additional pump in shutdown unit is
        were CW pump, CEP, CCW and CHP.
                                                                eliminated.

        How was the problem solved?
                                                                What were the challenges encountered?

        After  identifying  equipment  /  systems
                                                                Ensuring      equipment       reliability   and
        which have potential for improvement,
                                                                response during part load operation with
        following actions were initiated. Decision
                                                                variable load is a challenge after
        was  taken to  operate  one CCW pump  at
                                                                implementing changes in operational
        load  <  160  MW  as  the  flow  and  pressure
                                                                philosophy.
        was adequate for this load.


        Even though VFD in CEP was installed way
        back in 2014, scope for further reduction in

        power consumption was observed.
        A curve was incorporated in DCS logic for

        Auto changing of header pr. Set point w.r.t.
        load which not only eliminated risk of

        human error, but considerable savings in
        power consumption was achieved

        in CEP.



                                                                                                                   15
   14   15   16   17   18   19   20   21   22   23   24